IN THE SUPREME COURT OF NOVA SCOTIA

Citation: Alumitech Architectural Glass & Metal Ltd. v. J.W. Lindsay Enterprises Ltd., 2006 NSSC 14

 

Date: 20060116

Docket: S.H. 177985

Registry: Halifax

 

Between:

Alumitech Architectural Glass & Metal Limited

Plaintiff

Defendant by Counter-Claim

v.

 

J.W. Lindsay Enterprises Limited

Defendant

Plaintiff by Counter-Claim

 

LIBRARY HEADING

 

 

Judge:                   The Honourable Justice A. David MacAdam

 

Heard:                  December 20, 21, 22, 2005 in Halifax, Nova Scotia

 

Subject:                Contract - Quantum Meruit

 


Summary:             Plaintiff contracted with defendant.  The President of the plaintiff says he and the defendants representative,  although not agreeing on the square footage of the work to be performed by the defendant, agreed it was to be at a unit price per square foot.  The defendants, during or following the performance of the work, were to recalculate the square footage.  The defendants negotiator has since died.  Their estimator, who also attended the meeting with the President of the plaintiff, denied the agreement was for a unit price.  He said it was for a lump sum as appeared on the purchase order issued by the plaintiff.  Both parties agreed that if there was no consensus ad idem the compensation due the plaintiff was to be calculated on a quantum meruit.  The plaintiff suggested that a reasonable remuneration would be the unit price based on the plaintiffs calculation of the square footage of work.  The defendant tendered its costs to perform the work, which, together with a modest allowance for profit resulted in an amount equal to the lump sum figure being advanced by the defendant.

 

Issue:                  In applying the doctrine of Quantum Meruit how is reasonable compensation to be determined?

 

Result:                In determining reasonable compensation there  are four possibilities.

 

1.       Act on the evidence of the costs to perform the work, plus a reasonable allowance for profit;

2.       Act on evidence as to what reasonable rates would be;

3.       Consider aborted negotiations as to price;

4.       Consider the opinion of experts as to a reasonable sum.

 

Although acting on costs to perform, together with a reasonable allowance for profit, may have the effect of awarding one side their version of the amount contracted between the parties, when that partys version of the contract has not been accepted, this may be the only alternative when the other side produces no evidence to enable the reasonable compensation to be calculated by using one of the other alternatives and when it does not seriously challenge the costs estimates tendered.

 

 