Supreme Court

Decision Information

Decision Content

IN THE SUPREME COURT OF NOVA SCOTIA

Citation:  Force Construction Ltd. v.  Queen Elizabeth II Health Sciences Centre, 2008 NSSC 214

 

 

 

Date: 20080911

Docket: SH 174143

Registry:  Halifax

 

 

Between:

 

Force Construction Limited, a body corporate, and

Bell Electric Incorporated, a body corporate

 

                                                                                                                Plaintiffs

 

                                                             v.

 

Queen Elizabeth II Health Sciences Centre, a body

corporate

 

                                                                                                              Defendant

 

 

 

LIBRARY HEADING

 

 

Judge:                            The Honourable Justice C. Richard Coughlan

 

Heard:                            April 28, 29 and 30, May 5 and 6, 2008, in Halifax, Nova Scotia                      

 

Written Decision:  September 11, 2008

 

Subject:                          Contract - Tendering process - Duty to treat bidders fairly and equally    

 


 

 

Summary:                      The Queen Elizabeth Health Sciences Centre called a tender to construct its ophthalmology unit.  Force Construction submitted the lowest bid.  The Manager of Construction Services for the Hospital had previous experience with Force Construction having high unit labour rates.  Force Construction had the highest unit labour rates.  The Manager considered the practice of submitting high unit labour rates should be discouraged.  He assumed a contingency overun of 10% on the project’s cost, labour comprising 50% of the cost and all bidders using equivalent manhours.  He calculated Force Construction’s bid exceeded the second lowest bid by $1,187.00.  The tender was awarded to the second lowest bidder.  Force Construction and Bell Electric Incorporated, the electrical subcontractor on the Force Construction bid, sued the Hospital

 

Issue:          1)       Did the Hospital have a contract with Force Construction and, if so, did the Hospital breach the contract?

 

2)       If the Hospital breached its contract with Force Construction, to what damages is Force Construction entitled?

 

3)       Did the Hospital owe a duty of care to Bell Electric and, if so, did the Hospital breach the duty?

 

4)       If the Hospital breached its duty of care to Bell Electric, to what damages is Bell Electric entitled?

 

 

Result:                            The Hospital did not treat Force Construction fairly and equally, and therefore breached the contract it had with Force Construction and damages were assessed.

 


 

 

The Hospital did not owe a duty of care to Bell Electric and its claim was dismissed.

 

 

 

            THIS INFORMATION SHEET DOES NOT FORM PART OF THE COURT'S DECISION.            QUOTES MUST BE FROM THE DECISION, NOT THIS LIBRARY SHEET.

 You are being directed to the most recent version of the statute which may not be the version considered at the time of the judgment.